Tank Hill / Flood Restoration Works

  • Project Name: Tank Hill / Flood Restoration Works
  • Location: Highway 1 South of Spences Bridge, BC
  • Timeline End: October 31, 2021

Work included:

  • Mobilized 20+ pieces of highway equipment and 40 personnel in 48 hours on November 17, 2021
  • Assisted in the restoration and the reinstatement of the CP Rail mainline
  • Recommissioned Highway 1 with our group supplying and placing 240,000 m³
  • Worked 24 hours/day, seven days a week from November 17, 2021, until the CP rail was
    reinstated and operational on Nov 24/21, and Highway 1 was re-opened on January 15, 2022
  • More than 50,000 person-hours logged on this project with zero lost-time incidents